Edison Park Renovation Project Status

Below is an updated schedule for the Edison Park Renovation Project

Swales Park - Complete
Beatrice Park - Complete
Blossom Park - Complete
Capestro Park - Dirt stockpile to be removed week of 8/5.
**Proposal pending for modular block retaining wall/seat wall with drain pipe and stone to assist in preventing wash out onto the poured in place surfacing,
Edison Woods - Poured in place surfacing, landscaping remain.
Gateway Park - Concrete curbs, poured in place and landscaping remain.
Polansky Park - Commencing week of 8/5
Old Post Park - Commencing week of 8/12

** Above schedule may fluctuate due to any inclement weather.